Returns the number of work days between two dates taking into account the provided holiday dates.
Usage
countWorkDays(from, to, holiday = NULL, nonworkdays = c("Sat", "Sun"))Arguments
- from
initial dates
- to
final dates
- holiday
a vector of dates (or strings coercible with
as.Date()) to exclude- nonworkdays
a character vector containing the English three-letter weekday abbreviations to be treated as non-work days, i.e. a subset of
c("Mon", "Tue", "Wed", "Thu", "Fri", "Sat", "Sun"). Default isc("Sat", "Sun").
Details
The function is vectorised so that multiple initial and final dates can be supplied. The date vectors are recycled if their lengths differ.
Both endpoints are counted, so countWorkDays(d, d) is 1 for a
working day and 0 otherwise. A to that lies before from
yields 0.
Holidays outside the interval are ignored, as are holidays falling on a non-work day; duplicated holiday dates are counted once.
See also
Other date.time:
addMonths(),
date-time-predicates,
date_functions,
generation(),
time-conversions,
zodiac()
Examples
from <- as.Date("2019-01-01") + rep(0, 10)
to <- as.Date("2019-01-15") + seq(0, 9)
countWorkDays(from, to)
#> [1] 11 12 13 14 14 14 15 16 17 18
# which weekdays are involved
x <- seq(min(from), max(to), by = "days")
head(data.frame(date = x, day = weekday(x, fmt = "dd", lang = "en")))
#> date day
#> 1 2019-01-01 Tue
#> 2 2019-01-02 Wed
#> 3 2019-01-03 Thu
#> 4 2019-01-04 Fri
#> 5 2019-01-05 Sat
#> 6 2019-01-06 Sun
# two holidays inside the period reduce the count by two
countWorkDays(from = min(x), to = max(x))
#> [1] 18
countWorkDays(from = min(x), to = max(x),
holiday = c("2019-01-07", "2019-01-08"))
#> [1] 16
# a single day
countWorkDays(as.Date("2019-01-05"), as.Date("2019-01-05")) # Saturday: 0